Question 10
A regional network transformation proposal describes this situation: A public agency has an approved waterfall procurement but network architects silently substitute vendor features after contract award. Which measurable acceptance result most directly validates that design decision?
Explanation
Correct Answer
This measurable result validates the proposed architecture: Every substituted capability has an approved contract and acceptance mapping before installation. It directly checks the selected design (Document requirement-to-design traceability and submit deviations through formal impact review.) against the original requirements.
Incorrect Answers
This could validate a different design context: A healthcare network migration is judged complete when routers are installed even though clinicians cannot complete the patient-admission workflow. It does not demonstrate the necessary outcome for this case: Every substituted capability has an approved contract and acceptance mapping before installation.
This could validate a different design context: A logistics group runs Agile software sprints but each network change requires a month of cabling and carrier lead time. It does not demonstrate the necessary outcome for this case: Every substituted capability has an approved contract and acceptance mapping before installation.
This could validate a different design context: A CFO prefers a low initial purchase price, but a proposed private WAN requires expensive annual site visits and proprietary license renewals. It does not demonstrate the necessary outcome for this case: Every substituted capability has an approved contract and acceptance mapping before installation.