Question 80
At fictional Clearhaven Retail, the SPM implementation team is supporting a multi-region resource-planning environment. During a quarterly audit checkpoint, they find this specific issue: A resource manager counts both team members and their parent group as separate pools of hours when rolling up quarterly capacity. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Audit group membership and roll-up logic after organization changes. The check is important because capacity aggregation must preserve unique resource contributions across hierarchy levels.
Incorrect Answers
Include support windows and time zones in staffing acceptance. This is a separate preventive check. A total-hours match cannot establish availability during a particular time window. To address recurrence here, audit group membership and roll-up logic after organization changes.
Reconcile profile changes with training and staffing records periodically. This is a separate preventive check. Quality of planning attributes depends on governed workforce source records. To address recurrence here, audit group membership and roll-up logic after organization changes.
Check assignment hierarchy changes before regenerating demand. This is a separate preventive check. Aggregating parent demand and child execution effort can double count a single workload. To address recurrence here, audit group membership and roll-up logic after organization changes.