Question 440
At fictional Silverbrook Insurance, the SPM implementation team is supporting a project timecard and labor costing rollout. During a quarterly audit checkpoint, they find this specific issue: An integration retries a previously accepted timecard transmission and generates two approved records for the same person, date and task. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Monitor duplicate submissions and failed timecard integrations. The check is important because idempotent time-entry processing protects downstream actual costs against integration retries.
Incorrect Answers
Check planning date changes for downstream allocation effects. This is a separate preventive check. Capacity analysis is time-phased; the same effort in a different period is not interchangeable. To address recurrence here, monitor duplicate submissions and failed timecard integrations.
Review financial report definitions whenever new cost sources are integrated. This is a separate preventive check. Comparisons are meaningful only when their financial baseline and reporting periods are explicit. To address recurrence here, monitor duplicate submissions and failed timecard integrations.
Audit regional calendars before annual capacity plans are approved. This is a separate preventive check. Work schedules determine location-specific available capacity within the same portfolio. To address recurrence here, monitor duplicate submissions and failed timecard integrations.