Question 400
In an authorized test at fictional Birchgate Financial, the project team is assessing a multi-region program rollout. During a quarterly audit checkpoint, they find this specific issue: A team restores a prior project baseline as the active schedule without evaluating changes in dependencies and resource availability. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Reassess dependency and capacity assumptions for any baseline rollback. This prevents the same failure mode, in which a historic baseline is a comparison artifact, not proof that conditions still allow its original dates.
Incorrect Answers
Monitor stale ownership and unassigned demands each week. An intake record requires ongoing process ownership beyond the person who proposed it. It would not maintain the control needed here: reassess dependency and capacity assumptions for any baseline rollback.
Reassess external dependencies during demand-to-project handoff. Portfolio approval must consider constraints that determine whether funded work can actually start. It would not maintain the control needed here: reassess dependency and capacity assumptions for any baseline rollback.
Audit overrides and scoring outliers at portfolio decision meetings. A governed scoring process requires provenance, not only its latest numeric result. It would not maintain the control needed here: reassess dependency and capacity assumptions for any baseline rollback.