Question 220
In an authorized test at fictional Hawthorne Credit Union, the project team is assessing a regulated technology investment pipeline. During a quarterly audit checkpoint, they find this specific issue: An approved demand is manually recreated as an unrelated project and its risk and benefit assumptions disappear. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Audit converted projects for missing source references and approvals. This prevents the same failure mode, in which governed demand conversion should preserve portfolio decision lineage through execution.
Incorrect Answers
Review WBS completeness before accepting the baseline plan. A work breakdown structure conveys scope decomposition and aggregation rather than only a task list. It would not maintain the control needed here: audit converted projects for missing source references and approvals.
Review new idea clusters for duplicate outcomes before promotion. Intake deduplication reduces redundant work without discarding business stakeholders' distinct needs. It would not maintain the control needed here: audit converted projects for missing source references and approvals.
Reconcile visible items to source counts during each planning cycle. UI performance limits and filters can affect visibility without removing underlying plan records. It would not maintain the control needed here: audit converted projects for missing source references and approvals.