Question 270
For the documented project problem below, which outcome should be verified? A transport scheduling project has a project plan but lacks a detailed plan for the stage containing a safety-critical pilot.
Explanation
Correct Answer
Successful remediation is demonstrated when: The board authorizes a bounded pilot stage using a reviewable stage plan rather than an unsupported annual summary. That result connects to the targeted action: Prepare a stage plan with products, resources, controls and tolerances for the pilot before requesting authorization. The previously observed defect was: The project manager is using an aggregate plan where authorized stage-level control is required.
Incorrect Answers
The offered finding is relevant when the team manager and project manager lack an authorized statement of products, quality methods, limits and checkpoints. Here the acceptance test must show that the board authorizes a bounded pilot stage using a reviewable stage plan rather than an unsupported annual summary.
The observation relates to a problem where the plan lists effort and spending without a complete product breakdown structure; the required finding here is that the board authorizes a bounded pilot stage using a reviewable stage plan rather than an unsupported annual summary.
It would be evidence for a problem in which work package forecasts have not been refreshed for actual specialist capacity and workload. It does not verify that the board authorizes a bounded pilot stage using a reviewable stage plan rather than an unsupported annual summary.