Question 120
Choose the most relevant preventive check for this PRINCE2 project situation: A university payroll replacement delivers software on schedule, yet staff continue using spreadsheets because old processes were never retired.
Explanation
Correct Answer
This practice reduces the documented recurrence risk: Monitor process adoption after product handover through agreed operational ownership. The original root fault was: Change adoption and operational transition criteria have not been defined alongside technical acceptance. The practical health indicator is: Payroll runs use the new system with reconciled outputs and retired spreadsheets are no longer authoritative.
Incorrect Answers
The proposed routine targets situations in which the project has not analyzed incentives and behaviours affecting adoption of the changed process. To prevent the reported problem, the team must address the fact that change adoption and operational transition criteria have not been defined alongside technical acceptance.
The option addresses cases in which the transition has not recognized the effect of operating schedules on people delivering benefits. In the reported incident, change adoption and operational transition criteria have not been defined alongside technical acceptance instead.
The control would be appropriate if the change management approach treats technical installation as sufficient and neglects adoption readiness; the issue here is that change adoption and operational transition criteria have not been defined alongside technical acceptance.