Question 1
A PRINCE2 Project Management (Version 7) team faces this situation: A regional hospital modernization project has gained an expensive interface requirement after approval, and the forecast benefit no longer covers lifecycle costs. Which corrective governance or delivery action is most appropriate?
Explanation
Correct Answer
Update the business case with revised costs, risks and benefits and ask the project board to decide whether continuing is justified. This is the appropriate intervention because the original business justification is no longer demonstrated after the significant scope and cost change. The specific outcome to verify is: A documented board decision uses the updated forecast rather than the obsolete original return calculation.
Incorrect Answers
“Escalate the lost business rationale to the executive and project board for a continue, change or stop decision” is useful when the project team is treating technical delivery success as a substitute for ongoing business justification. It does not resolve the current problem, in which the original business justification is no longer demonstrated after the significant scope and cost change.
That action tackles a problem where undefined delegation creates conflicting day-to-day decisions and no single manager accountable for stage control. The reported issue is instead that the original business justification is no longer demonstrated after the significant scope and cost change.
This change addresses a situation in which the project has not connected adoption evidence to the continuing desirability and viability of the business case. It leaves the current failure unresolved because the original business justification is no longer demonstrated after the significant scope and cost change.