McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 70

Question 690

The project issue was: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. Which outcome demonstrates that its remedy worked?

  1. The test plan contains measurable response, reliability and defect thresholds.
  2. The risk register contains uncertain event descriptions, owners and responses.
  3. The sponsor signs an initiation decision using current values and confidence levels.
  4. Both teams reference one approved requirement and implementation decision.

Explanation

Correct Answer

B:

The risk register contains uncertain event descriptions, owners and responses. This validates the selected response: Separate stakeholder issues from prospective risk statements and maintain appropriate logs. The relevant management principle is: Information artifacts are useful when entries match their intended decision purpose.

Incorrect Answers

A:

The test plan contains measurable response, reliability and defect thresholds. This is evidence for ANOTHER case: A quality plan specifies that software must be excellent but has no measurable tests. The specific corrective response here is: Separate stakeholder issues from prospective risk statements and maintain appropriate logs.

C:

The sponsor signs an initiation decision using current values and confidence levels. This is evidence for ANOTHER case: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate. The specific corrective response here is: Separate stakeholder issues from prospective risk statements and maintain appropriate logs.

D:

Both teams reference one approved requirement and implementation decision. This is evidence for ANOTHER case: Two teams interpret an executive statement differently and begin incompatible implementations. The specific corrective response here is: Separate stakeholder issues from prospective risk statements and maintain appropriate logs.

Question 691

For a financial-services implementation team, the documented failure was: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. Which explanation is most accurate?

  1. Product plans describe evolving product direction while project plans govern a specific undertaking.
  2. Resource planning considers skills and timing as well as number of people.
  3. Information artifacts are useful when entries match their intended decision purpose.
  4. Realized adverse events need issue management rather than only assumption tracking.

Explanation

Correct Answer

C:

Information artifacts are useful when entries match their intended decision purpose. This explains the case: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. The targeted action is: Separate stakeholder issues from prospective risk statements and maintain appropriate logs.

Incorrect Answers

A:

Product plans describe evolving product direction while project plans govern a specific undertaking. This rationale better explains a DIFFERENT problem: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. The key mechanism for the current situation is: Information artifacts are useful when entries match their intended decision purpose.

B:

Resource planning considers skills and timing as well as number of people. This rationale better explains a DIFFERENT problem: A remote migration is staffed with four developers although the schedule requires one specialized network reviewer unavailable that month. The key mechanism for the current situation is: Information artifacts are useful when entries match their intended decision purpose.

D:

Realized adverse events need issue management rather than only assumption tracking. This rationale better explains a DIFFERENT problem: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. The key mechanism for the current situation is: Information artifacts are useful when entries match their intended decision purpose.

Question 692

Which recurring governance check best addresses the risk of repeating: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses.

  1. Use closure readiness criteria with required compliance items.
  2. Revalidate stakeholder records after organizational changes.
  3. Include end-state ownership in facility-change proposals.
  4. Train contributors on register classification and fields.

Explanation

Correct Answer

D:

Train contributors on register classification and fields. This helps prevent recurrence of: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. The required evidence of effective control is: The risk register contains uncertain event descriptions, owners and responses.

Incorrect Answers

A:

Use closure readiness criteria with required compliance items. That is a useful control for ANOTHER case: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. The current situation is better prevented by: Train contributors on register classification and fields.

B:

Revalidate stakeholder records after organizational changes. That is a useful control for ANOTHER case: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The current situation is better prevented by: Train contributors on register classification and fields.

C:

Include end-state ownership in facility-change proposals. That is a useful control for ANOTHER case: A temporary warehouse relocation has a defined final operating site, but managers treat it as routine daily warehousing. The current situation is better prevented by: Train contributors on register classification and fields.

Question 693

During a project review, stakeholders report: Two teams interpret an executive statement differently and begin incompatible implementations. What should the team do first?

  1. Gather facts privately, manage emotions and negotiate an equitable next step.
  2. Facilitate a shared understanding and confirm decisions with affected stakeholders.
  3. Acknowledge concerns, clarify interests and facilitate an evidence-based resolution.
  4. Identify the receiving operational owner and transfer acceptance requirements during planning.

Explanation

Correct Answer

B:

Facilitate a shared understanding and confirm decisions with affected stakeholders. This addresses the fictional case: Two teams interpret an executive statement differently and begin incompatible implementations. The project-management rationale is: Listening and facilitation help turn ambiguous directions into aligned work. Verify by: Both teams reference one approved requirement and implementation decision.

Incorrect Answers

A:

Gather facts privately, manage emotions and negotiate an equitable next step. This would address a DIFFERENT fictional project situation: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides. It is less directly applicable to: Two teams interpret an executive statement differently and begin incompatible implementations.

C:

Acknowledge concerns, clarify interests and facilitate an evidence-based resolution. This would address a DIFFERENT fictional project situation: A customer review becomes confrontational because the manager dismisses frustration as irrelevant to technical status. It is less directly applicable to: Two teams interpret an executive statement differently and begin incompatible implementations.

D:

Identify the receiving operational owner and transfer acceptance requirements during planning. This would address a DIFFERENT fictional project situation: A sponsor signs off a marketing campaign but never decides who operates the online channel after launch. It is less directly applicable to: Two teams interpret an executive statement differently and begin incompatible implementations.

Question 694

Following the proposed correction, what observation confirms success: Two teams interpret an executive statement differently and begin incompatible implementations.

  1. A decision log captures trade-offs and explicit authority rather than unverified promises.
  2. Experts confirm that the documented constraints reflect their input.
  3. Both teams reference one approved requirement and implementation decision.
  4. The sponsor receives timely, accurate escalation and options.

Explanation

Correct Answer

C:

Both teams reference one approved requirement and implementation decision. This validates the selected response: Facilitate a shared understanding and confirm decisions with affected stakeholders. The relevant management principle is: Listening and facilitation help turn ambiguous directions into aligned work.

Incorrect Answers

A:

A decision log captures trade-offs and explicit authority rather than unverified promises. This is evidence for ANOTHER case: A sponsor promises an impossible delivery date, then blames the team when technical evidence contradicts it. The specific corrective response here is: Facilitate a shared understanding and confirm decisions with affected stakeholders.

B:

Experts confirm that the documented constraints reflect their input. This is evidence for ANOTHER case: An inexperienced coordinator repeatedly interrupts senior subject experts and misses material project constraints. The specific corrective response here is: Facilitate a shared understanding and confirm decisions with affected stakeholders.

D:

The sponsor receives timely, accurate escalation and options. This is evidence for ANOTHER case: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. The specific corrective response here is: Facilitate a shared understanding and confirm decisions with affected stakeholders.

Question 695

Which underlying planning or business-analysis mechanism explains: Two teams interpret an executive statement differently and begin incompatible implementations.

  1. Psychological safety and self-awareness support honest risk disclosure.
  2. Leadership builds effectiveness through influence and support, not only positional control.
  3. PMI's ethical expectations emphasize honesty, responsibility, respect and fairness.
  4. Listening and facilitation help turn ambiguous directions into aligned work.

Explanation

Correct Answer

D:

Listening and facilitation help turn ambiguous directions into aligned work. This explains the case: Two teams interpret an executive statement differently and begin incompatible implementations. The targeted action is: Facilitate a shared understanding and confirm decisions with affected stakeholders.

Incorrect Answers

A:

Psychological safety and self-awareness support honest risk disclosure. This rationale better explains a DIFFERENT problem: The project manager responds defensively to a quality finding and discourages testers from reporting defects. The key mechanism for the current situation is: Listening and facilitation help turn ambiguous directions into aligned work.

B:

Leadership builds effectiveness through influence and support, not only positional control. This rationale better explains a DIFFERENT problem: An agile facilitator evaluates team success by how many direct orders team members obey. The key mechanism for the current situation is: Listening and facilitation help turn ambiguous directions into aligned work.

C:

PMI's ethical expectations emphasize honesty, responsibility, respect and fairness. This rationale better explains a DIFFERENT problem: A procurement manager requests a hidden bid advantage from a supplier in exchange for confidential evaluation scores. The key mechanism for the current situation is: Listening and facilitation help turn ambiguous directions into aligned work.

Question 696

For the previous project issue, select the best preventive control: Two teams interpret an executive statement differently and begin incompatible implementations.

  1. Use decision summaries with explicit owners.
  2. Coach new coordinators in structured facilitation.
  3. Make change approval rights visible to customer representatives.
  4. Include decision limits and trigger tests in risk playbooks.

Explanation

Correct Answer

A:

Use decision summaries with explicit owners. This helps prevent recurrence of: Two teams interpret an executive statement differently and begin incompatible implementations. The required evidence of effective control is: Both teams reference one approved requirement and implementation decision.

Incorrect Answers

B:

Coach new coordinators in structured facilitation. That is a useful control for ANOTHER case: An inexperienced coordinator repeatedly interrupts senior subject experts and misses material project constraints. The current situation is better prevented by: Use decision summaries with explicit owners.

C:

Make change approval rights visible to customer representatives. That is a useful control for ANOTHER case: A PM is assigned to a project without authority to approve scope but tells customers every feature request is automatically accepted. The current situation is better prevented by: Use decision summaries with explicit owners.

D:

Include decision limits and trigger tests in risk playbooks. That is a useful control for ANOTHER case: The risk owner identifies a trigger but refuses to act until the project manager attends the next meeting. The current situation is better prevented by: Use decision summaries with explicit owners.

Question 697

For a construction planning unit, a delivery problem is reported: A project initiation memo promises growth but includes no baseline of current performance. Which action fits the situation?

  1. Follow the procurement response plan, assess new impacts and notify affected stakeholders.
  2. Assign benefit ownership and tie prioritized scope to approved value measures.
  3. Define current-state measures and target benefits in the initiation business case.
  4. Report the accurate estimate and supporting uncertainty through established governance.

Explanation

Correct Answer

C:

Define current-state measures and target benefits in the initiation business case. This addresses the fictional case: A project initiation memo promises growth but includes no baseline of current performance. The project-management rationale is: Without a benchmark, claiming realized change is not testable. Verify by: Governance can compare proposed investment against an objective baseline.

Incorrect Answers

A:

Follow the procurement response plan, assess new impacts and notify affected stakeholders. This would address a DIFFERENT fictional project situation: A project closes its schedule report when a vendor refuses delivery, despite an established procurement contingency. It is less directly applicable to: A project initiation memo promises growth but includes no baseline of current performance.

B:

Assign benefit ownership and tie prioritized scope to approved value measures. This would address a DIFFERENT fictional project situation: A sponsor approved a high-level benefit target, but the project team starts building unrelated features because no value owner is identified. It is less directly applicable to: A project initiation memo promises growth but includes no baseline of current performance.

D:

Report the accurate estimate and supporting uncertainty through established governance. This would address a DIFFERENT fictional project situation: A project analyst learns that a published milestone estimate was deliberately misrepresented to win approval. It is less directly applicable to: A project initiation memo promises growth but includes no baseline of current performance.

Question 698

How should the project team verify a successful response to: A project initiation memo promises growth but includes no baseline of current performance.

  1. Escalation logs show appropriate priority and reduced unnecessary interruptions.
  2. A benefits register states target measures, owner and validation method.
  3. The estimate includes shared scope assumptions and visible uncertainty.
  4. Governance can compare proposed investment against an objective baseline.

Explanation

Correct Answer

D:

Governance can compare proposed investment against an objective baseline. This validates the selected response: Define current-state measures and target benefits in the initiation business case. The relevant management principle is: Without a benchmark, claiming realized change is not testable.

Incorrect Answers

A:

Escalation logs show appropriate priority and reduced unnecessary interruptions. This is evidence for ANOTHER case: A team labels every low-impact schedule concern as an emergency despite a tiered escalation strategy. The specific corrective response here is: Define current-state measures and target benefits in the initiation business case.

B:

A benefits register states target measures, owner and validation method. This is evidence for ANOTHER case: A charity launches a fundraising technology project without documenting how the delivered platform advances target donations. The specific corrective response here is: Define current-state measures and target benefits in the initiation business case.

C:

The estimate includes shared scope assumptions and visible uncertainty. This is evidence for ANOTHER case: A planning team asks employees to estimate a complex migration separately but then averages incompatible assumptions without discussion. The specific corrective response here is: Define current-state measures and target benefits in the initiation business case.

Question 699

A project team asks why this occurs: A project initiation memo promises growth but includes no baseline of current performance. Which project management principle best explains it?

  1. Without a benchmark, claiming realized change is not testable.
  2. Communication strategy includes appropriate confidentiality and audience selection.
  3. Communication planning matches detail and frequency to audience needs.
  4. A schedule alone cannot address uncertain threats to project objectives.

Explanation

Correct Answer

A:

Without a benchmark, claiming realized change is not testable. This explains the case: A project initiation memo promises growth but includes no baseline of current performance. The targeted action is: Define current-state measures and target benefits in the initiation business case.

Incorrect Answers

B:

Communication strategy includes appropriate confidentiality and audience selection. This rationale better explains a DIFFERENT problem: Project teams send confidential risk details to a broad mailing list despite a stakeholder communication plan limiting distribution. The key mechanism for the current situation is: Without a benchmark, claiming realized change is not testable.

C:

Communication planning matches detail and frequency to audience needs. This rationale better explains a DIFFERENT problem: A communications coordinator sends a highly technical daily report to executives whose plan calls for a monthly decision dashboard. The key mechanism for the current situation is: Without a benchmark, claiming realized change is not testable.

D:

A schedule alone cannot address uncertain threats to project objectives. This rationale better explains a DIFFERENT problem: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. The key mechanism for the current situation is: Without a benchmark, claiming realized change is not testable.

Question 700

At a construction planning unit, the team wants to avoid repeating: A project initiation memo promises growth but includes no baseline of current performance. Which safeguard should it retain?

  1. Check distribution permissions in sensitive status templates.
  2. Validate benefit baselines before budget approval.
  3. Trigger benefit-plan review on substantial objective changes.
  4. Make change approval rights visible to customer representatives.

Explanation

Correct Answer

B:

Validate benefit baselines before budget approval. This helps prevent recurrence of: A project initiation memo promises growth but includes no baseline of current performance. The required evidence of effective control is: Governance can compare proposed investment against an objective baseline.

Incorrect Answers

A:

Check distribution permissions in sensitive status templates. That is a useful control for ANOTHER case: Project teams send confidential risk details to a broad mailing list despite a stakeholder communication plan limiting distribution. The current situation is better prevented by: Validate benefit baselines before budget approval.

C:

Trigger benefit-plan review on substantial objective changes. That is a useful control for ANOTHER case: A sponsor changes the project purpose from cost savings to regulatory compliance without reexamining planned outcomes. The current situation is better prevented by: Validate benefit baselines before budget approval.

D:

Make change approval rights visible to customer representatives. That is a useful control for ANOTHER case: A PM is assigned to a project without authority to approve scope but tells customers every feature request is automatically accepted. The current situation is better prevented by: Validate benefit baselines before budget approval.