Question 610
The project issue was: A hospital rollout must use approved encryption regardless of cost, but staff record this mandatory condition as an optional risk. Which outcome demonstrates that its remedy worked?
Explanation
Correct Answer
The approved solution meets the immutable security requirement. This validates the selected response: Register encryption compliance as a project constraint and plan delivery within it. The relevant management principle is: Constraints restrict possible choices, whereas risks describe uncertain effects.
Incorrect Answers
A revised prioritized scope demonstrates feedback-informed product direction through governance. This is evidence for ANOTHER case: A market-testing initiative keeps an immutable specification after customer interviews reveal the solution solves the wrong need. The specific corrective response here is: Register encryption compliance as a project constraint and plan delivery within it.
Baseline approvals demonstrate that planned commitments stay within the approved cap. This is evidence for ANOTHER case: A finance team treats a capped annual funding limit as an unknown risk rather than a fixed spending boundary. The specific corrective response here is: Register encryption compliance as a project constraint and plan delivery within it.
Experts confirm that the documented constraints reflect their input. This is evidence for ANOTHER case: An inexperienced coordinator repeatedly interrupts senior subject experts and misses material project constraints. The specific corrective response here is: Register encryption compliance as a project constraint and plan delivery within it.