Question 570
How should the project team verify a successful response to: A sprint review shows features built but no acceptance criteria agreed with stakeholders.
Explanation
Correct Answer
The completed increment passes agreed user-visible checks. This validates the selected response: Define testable acceptance criteria for backlog items before completion decisions. The relevant management principle is: Adaptive acceptance requires shared definitions of done and desired behavior.
Incorrect Answers
The next iteration selects high-value feasible work from an ordered backlog. This is evidence for ANOTHER case: A release backlog lists capabilities with no ordering although customer value and dependencies differ widely. The specific corrective response here is: Define testable acceptance criteria for backlog items before completion decisions.
Review dates and team planning rhythm become predictable. This is evidence for ANOTHER case: An agile team changes sprint duration every week because a manager wants reports earlier. The specific corrective response here is: Define testable acceptance criteria for backlog items before completion decisions.
Participating teams can trace work to an agreed release objective. This is evidence for ANOTHER case: A program team adopts scaled ceremonies but retains conflicting product priorities across four component teams. The specific corrective response here is: Define testable acceptance criteria for backlog items before completion decisions.