McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 49

Question 480

What ongoing preventive practice would most reduce recurrence of: A transit modernization project combines commissioning tests and public activation into one work package despite mandatory test signoff.

  1. Review regulatory dependencies with procurement partners.
  2. Assess requirement stability before selecting the delivery lifecycle.
  3. Check approval prerequisites in dependency reviews.
  4. Audit cross-vendor interface agreements before testing.

Explanation

Correct Answer

C:

Check approval prerequisites in dependency reviews. This helps prevent recurrence of: A transit modernization project combines commissioning tests and public activation into one work package despite mandatory test signoff. The required evidence of effective control is: The activation cannot begin until verified commissioning acceptance is recorded.

Incorrect Answers

A:

Review regulatory dependencies with procurement partners. That is a useful control for ANOTHER case: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. The current situation is better prevented by: Check approval prerequisites in dependency reviews.

B:

Assess requirement stability before selecting the delivery lifecycle. That is a useful control for ANOTHER case: A power-station upgrade has fixed regulatory specifications but a team proposes changing foundational requirements every week. The current situation is better prevented by: Check approval prerequisites in dependency reviews.

D:

Audit cross-vendor interface agreements before testing. That is a useful control for ANOTHER case: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The current situation is better prevented by: Check approval prerequisites in dependency reviews.

Question 481

At a construction planning unit, the review identifies: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. Which response best addresses the specific project management problem?

  1. Create a deliverable-oriented WBS and identify workable control-account and work-package levels.
  2. Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations.
  3. Correct the logical dependency so prototype acceptance precedes assembly.
  4. Maintain the distinct integrated project execution plans and product requirements baseline.

Explanation

Correct Answer

A:

Create a deliverable-oriented WBS and identify workable control-account and work-package levels. This addresses the fictional case: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. The project-management rationale is: WBS decomposition defines scope deliverables rather than merely replicating time sheets. Verify by: Each scheduled activity traces to an accepted WBS work package.

Incorrect Answers

B:

Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations. This would address a DIFFERENT fictional project situation: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. It is less directly applicable to: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables.

C:

Correct the logical dependency so prototype acceptance precedes assembly. This would address a DIFFERENT fictional project situation: A manufacturing engineer schedules final assembly before a required prototype test because both have available staff. It is less directly applicable to: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables.

D:

Maintain the distinct integrated project execution plans and product requirements baseline. This would address a DIFFERENT fictional project situation: A fixed-budget compliance initiative treats its product requirements list as a substitute for schedule, cost and risk plans. It is less directly applicable to: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables.

Question 482

The project issue was: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. Which outcome demonstrates that its remedy worked?

  1. The status sheet records SV = −$10,000 with context about being behind planned value.
  2. Each scheduled activity traces to an accepted WBS work package.
  3. The schedule contains the approval event linked to the correct predecessor work.
  4. The sheet independently presents accurate CV and SV fields.

Explanation

Correct Answer

B:

Each scheduled activity traces to an accepted WBS work package. This validates the selected response: Create a deliverable-oriented WBS and identify workable control-account and work-package levels. The relevant management principle is: WBS decomposition defines scope deliverables rather than merely replicating time sheets.

Incorrect Answers

A:

The status sheet records SV = −$10,000 with context about being behind planned value. This is evidence for ANOTHER case: A project reports earned value of $40,000 and planned value of $50,000 but describes its schedule variance as positive. The specific corrective response here is: Create a deliverable-oriented WBS and identify workable control-account and work-package levels.

C:

The schedule contains the approval event linked to the correct predecessor work. This is evidence for ANOTHER case: A team calls a zero-effort contract signoff a work package requiring three engineers for two weeks. The specific corrective response here is: Create a deliverable-oriented WBS and identify workable control-account and work-package levels.

D:

The sheet independently presents accurate CV and SV fields. This is evidence for ANOTHER case: A project status sheet calculates cost variance as PV−AC, masking the fact that earned value is lower than planned. The specific corrective response here is: Create a deliverable-oriented WBS and identify workable control-account and work-package levels.

Question 483

For a construction planning unit, the documented failure was: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. Which explanation is most accurate?

  1. Integration management aligns dependent deliverables into a working whole.
  2. Concurrent network paths do not simply accumulate elapsed time.
  3. WBS decomposition defines scope deliverables rather than merely replicating time sheets.
  4. Distinct project components require coordinated but identifiable responsibilities.

Explanation

Correct Answer

C:

WBS decomposition defines scope deliverables rather than merely replicating time sheets. This explains the case: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. The targeted action is: Create a deliverable-oriented WBS and identify workable control-account and work-package levels.

Incorrect Answers

A:

Integration management aligns dependent deliverables into a working whole. This rationale better explains a DIFFERENT problem: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The key mechanism for the current situation is: WBS decomposition defines scope deliverables rather than merely replicating time sheets.

B:

Concurrent network paths do not simply accumulate elapsed time. This rationale better explains a DIFFERENT problem: A dependency graph shows two parallel work paths of 14 and 11 days, and the team adds both to forecast a 25-day project. The key mechanism for the current situation is: WBS decomposition defines scope deliverables rather than merely replicating time sheets.

D:

Distinct project components require coordinated but identifiable responsibilities. This rationale better explains a DIFFERENT problem: A project lists stakeholder acceptance and maintenance training as tasks inside design engineering without distinct owners. The key mechanism for the current situation is: WBS decomposition defines scope deliverables rather than merely replicating time sheets.

Question 484

Which recurring governance check best addresses the risk of repeating: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables.

  1. Reject unverifiable single-package baselines for complex scopes.
  2. Track deferred inspections as controlled risks and issues.
  3. Review regulatory dependencies with procurement partners.
  4. Check that the WBS covers total accepted scope.

Explanation

Correct Answer

D:

Check that the WBS covers total accepted scope. This helps prevent recurrence of: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. The required evidence of effective control is: Each scheduled activity traces to an accepted WBS work package.

Incorrect Answers

A:

Reject unverifiable single-package baselines for complex scopes. That is a useful control for ANOTHER case: A plan uses one undifferentiated task called build hospital with no deliverable ownership or progress measure. The current situation is better prevented by: Check that the WBS covers total accepted scope.

B:

Track deferred inspections as controlled risks and issues. That is a useful control for ANOTHER case: A quality plan defines required defect thresholds but the test lead skips an inspection to protect a date milestone. The current situation is better prevented by: Check that the WBS covers total accepted scope.

C:

Review regulatory dependencies with procurement partners. That is a useful control for ANOTHER case: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. The current situation is better prevented by: Check that the WBS covers total accepted scope.

Question 485

During a project review, stakeholders report: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. What should the team do first?

  1. Calculate performance using earned work value and incurred cost rather than cash timing alone.
  2. Compute the supported schedule variance and interpret earned work relative to plan.
  3. Reconcile AC and EV components and investigate measurable underlying cost drivers.
  4. Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule.

Explanation

Correct Answer

B:

Compute the supported schedule variance and interpret earned work relative to plan. This addresses the fictional case: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. The project-management rationale is: Earned-value schedule metrics evaluate work accomplished, not elapsed time alone. Verify by: The report shows SV −$20,000 and an explained mitigation proposal.

Incorrect Answers

A:

Calculate performance using earned work value and incurred cost rather than cash timing alone. This would address a DIFFERENT fictional project situation: A contract administrator reports a favorable monthly cash flow and assumes project cost performance is therefore favorable. It is less directly applicable to: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery.

C:

Reconcile AC and EV components and investigate measurable underlying cost drivers. This would address a DIFFERENT fictional project situation: A project office receives an adverse CV but attributes it to schedule delay without inspecting invoice timing or delivery efficiency. It is less directly applicable to: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery.

D:

Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule. This would address a DIFFERENT fictional project situation: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. It is less directly applicable to: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery.

Question 486

Following the proposed correction, what observation confirms success: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery.

  1. Earned-value records tie progress to defined deliverable measurement criteria.
  2. The sheet independently presents accurate CV and SV fields.
  3. The report shows SV −$20,000 and an explained mitigation proposal.
  4. A reviewable schedule links procurement, installation and inspection in the required order.

Explanation

Correct Answer

C:

The report shows SV −$20,000 and an explained mitigation proposal. This validates the selected response: Compute the supported schedule variance and interpret earned work relative to plan. The relevant management principle is: Earned-value schedule metrics evaluate work accomplished, not elapsed time alone.

Incorrect Answers

A:

Earned-value records tie progress to defined deliverable measurement criteria. This is evidence for ANOTHER case: A project measures its entire progress solely by number of tasks started, not accepted work packages. The specific corrective response here is: Compute the supported schedule variance and interpret earned work relative to plan.

B:

The sheet independently presents accurate CV and SV fields. This is evidence for ANOTHER case: A project status sheet calculates cost variance as PV−AC, masking the fact that earned value is lower than planned. The specific corrective response here is: Compute the supported schedule variance and interpret earned work relative to plan.

D:

A reviewable schedule links procurement, installation and inspection in the required order. This is evidence for ANOTHER case: A manufacturing renovation has clear specifications and sequential safety inspections, yet the team cannot identify which activities must finish before others begin. The specific corrective response here is: Compute the supported schedule variance and interpret earned work relative to plan.

Question 487

Which underlying planning or business-analysis mechanism explains: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery.

  1. Negative cost variance means actual cost exceeds the value of completed work.
  2. Cash movements and earned-value cost efficiency measure different phenomena.
  3. Extra time on an unchanged critical path extends completion absent other schedule adjustments.
  4. Earned-value schedule metrics evaluate work accomplished, not elapsed time alone.

Explanation

Correct Answer

D:

Earned-value schedule metrics evaluate work accomplished, not elapsed time alone. This explains the case: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. The targeted action is: Compute the supported schedule variance and interpret earned work relative to plan.

Incorrect Answers

A:

Negative cost variance means actual cost exceeds the value of completed work. This rationale better explains a DIFFERENT problem: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The key mechanism for the current situation is: Earned-value schedule metrics evaluate work accomplished, not elapsed time alone.

B:

Cash movements and earned-value cost efficiency measure different phenomena. This rationale better explains a DIFFERENT problem: A contract administrator reports a favorable monthly cash flow and assumes project cost performance is therefore favorable. The key mechanism for the current situation is: Earned-value schedule metrics evaluate work accomplished, not elapsed time alone.

C:

Extra time on an unchanged critical path extends completion absent other schedule adjustments. This rationale better explains a DIFFERENT problem: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration. The key mechanism for the current situation is: Earned-value schedule metrics evaluate work accomplished, not elapsed time alone.

Question 488

For the previous project issue, select the best preventive control: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery.

  1. Compare EV and PV at every reporting cutoff.
  2. Include sign checks in financial reporting scripts.
  3. Review supplier-held baselines after integrated changes.
  4. Apply a 100-percent scope reconciliation review.

Explanation

Correct Answer

A:

Compare EV and PV at every reporting cutoff. This helps prevent recurrence of: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. The required evidence of effective control is: The report shows SV −$20,000 and an explained mitigation proposal.

Incorrect Answers

B:

Include sign checks in financial reporting scripts. That is a useful control for ANOTHER case: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The current situation is better prevented by: Compare EV and PV at every reporting cutoff.

C:

Review supplier-held baselines after integrated changes. That is a useful control for ANOTHER case: A government project holds a scope baseline but shares no signed schedule version with its suppliers. The current situation is better prevented by: Compare EV and PV at every reporting cutoff.

D:

Apply a 100-percent scope reconciliation review. That is a useful control for ANOTHER case: A project WBS lists training twice in separate branches and leaves operational handover out completely. The current situation is better prevented by: Compare EV and PV at every reporting cutoff.

Question 489

For a cross-functional software product team, a delivery problem is reported: A safety-critical pharmaceutical build has fixed validation gates but uncertain training content based on early users. Which action fits the situation?

  1. Negotiate stable team capacity and workable collaboration arrangements before committing to iterative cadence.
  2. Establish a product ownership decision role and agreed prioritization authority.
  3. Use a hybrid plan combining governed safety deliverables and iterative training refinement.
  4. Select realistic sprint scope from empirical velocity and available capacity.

Explanation

Correct Answer

C:

Use a hybrid plan combining governed safety deliverables and iterative training refinement. This addresses the fictional case: A safety-critical pharmaceutical build has fixed validation gates but uncertain training content based on early users. The project-management rationale is: Different components of the same initiative may need different delivery methods. Verify by: Mandatory compliance approvals and flexible training iterations are separately controlled.

Incorrect Answers

A:

Negotiate stable team capacity and workable collaboration arrangements before committing to iterative cadence. This would address a DIFFERENT fictional project situation: A matrix organization prevents team members from dedicating any regular time to the selected agile work. It is less directly applicable to: A safety-critical pharmaceutical build has fixed validation gates but uncertain training content based on early users.

B:

Establish a product ownership decision role and agreed prioritization authority. This would address a DIFFERENT fictional project situation: A team has no empowered representative to make product trade-offs during short iterations. It is less directly applicable to: A safety-critical pharmaceutical build has fixed validation gates but uncertain training content based on early users.

D:

Select realistic sprint scope from empirical velocity and available capacity. This would address a DIFFERENT fictional project situation: A Scrum team schedules six weeks of work in a two-week sprint despite its recent capacity being stable and lower. It is less directly applicable to: A safety-critical pharmaceutical build has fixed validation gates but uncertain training content based on early users.

Question 490

How should the project team verify a successful response to: A safety-critical pharmaceutical build has fixed validation gates but uncertain training content based on early users.

  1. The team demonstrates working increments and incorporates approved findings promptly.
  2. Early users evaluate a minimum usable release before later backlog commitments.
  3. Representative users with assistive technology pass the acceptance test.
  4. Mandatory compliance approvals and flexible training iterations are separately controlled.

Explanation

Correct Answer

D:

Mandatory compliance approvals and flexible training iterations are separately controlled. This validates the selected response: Use a hybrid plan combining governed safety deliverables and iterative training refinement. The relevant management principle is: Different components of the same initiative may need different delivery methods.

Incorrect Answers

A:

The team demonstrates working increments and incorporates approved findings promptly. This is evidence for ANOTHER case: A new patient portal's requirements change after each usability trial but leaders demand that all details be frozen a year ahead. The specific corrective response here is: Use a hybrid plan combining governed safety deliverables and iterative training refinement.

B:

Early users evaluate a minimum usable release before later backlog commitments. This is evidence for ANOTHER case: A startup has rapidly changing market assumptions, yet its governance requires one fixed release containing every requested feature. The specific corrective response here is: Use a hybrid plan combining governed safety deliverables and iterative training refinement.

C:

Representative users with assistive technology pass the acceptance test. This is evidence for ANOTHER case: A product team accepts a report feature that fails accessibility needs because acceptance tests considered only functionality. The specific corrective response here is: Use a hybrid plan combining governed safety deliverables and iterative training refinement.