Question 450
The project issue was: A business analyst promotes every proposed backlog item to scope baseline in an agile product, preventing legitimate reprioritization. Which outcome demonstrates that its remedy worked?
Explanation
Correct Answer
Stakeholders can see current priorities without treating all future ideas as fixed scope. This validates the selected response: Differentiate evolving backlog candidates from currently committed increment objectives and governance constraints. The relevant management principle is: Agile BA adapts anticipated work while managing specific commitments.
Incorrect Answers
Contract revisions and design specifications remain synchronized. This is evidence for ANOTHER case: A predictive procurement project repeatedly changes interface specifications by chat without evaluating cost or contractual consequences. The specific corrective response here is: Differentiate evolving backlog candidates from currently committed increment objectives and governance constraints.
Each increment has current accepted requirements with feedback incorporated. This is evidence for ANOTHER case: An agile team freezes business analysis until a six-month requirements document is signed, delaying feedback from early increments. The specific corrective response here is: Differentiate evolving backlog candidates from currently committed increment objectives and governance constraints.
The critical defect is fixed and regression tests pass before release. This is evidence for ANOTHER case: An agile release candidate has passed tests but a newly discovered security defect violates an agreed mandatory criterion. The specific corrective response here is: Differentiate evolving backlog candidates from currently committed increment objectives and governance constraints.