Question 410
How should the project team verify a successful response to: A schedule control board receives a late delivery forecast but the project report fails to distinguish a revised forecast from approved baseline.
Explanation
Correct Answer
The variance report shows actual forecast change without silently resetting targets. This validates the selected response: Track current forecast and approved baseline as separate configuration-controlled artifacts. The relevant management principle is: Predictive control depends on an approved reference against which performance is assessed.
Incorrect Answers
Reports reference the correct approved revision effective date. This is evidence for ANOTHER case: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. The specific corrective response here is: Track current forecast and approved baseline as separate configuration-controlled artifacts.
Earned-value records tie progress to defined deliverable measurement criteria. This is evidence for ANOTHER case: A project measures its entire progress solely by number of tasks started, not accepted work packages. The specific corrective response here is: Track current forecast and approved baseline as separate configuration-controlled artifacts.
Proposed changes receive documented impact review and correct approval before implementation. This is evidence for ANOTHER case: A construction PM begins executing a fully specified plan but no one knows when baseline changes require sponsor approval. The specific corrective response here is: Track current forecast and approved baseline as separate configuration-controlled artifacts.