McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 39

Question 380

At a small product delivery team, the team wants to avoid repeating: A sponsor asks the BA to accept a feature because the vendor says it is complete, but no user criteria were recorded. Which safeguard should it retain?

  1. Require end-to-end acceptance cases for major releases.
  2. Require customer-visible acceptance measures in contracts.
  3. Include integration dependencies in release gate reviews.
  4. Include non-user oversight bodies in stakeholder mapping.

Explanation

Correct Answer

B:

Require customer-visible acceptance measures in contracts. This helps prevent recurrence of: A sponsor asks the BA to accept a feature because the vendor says it is complete, but no user criteria were recorded. The required evidence of effective control is: Approval follows verified results instead of vendor declaration alone.

Incorrect Answers

A:

Require end-to-end acceptance cases for major releases. That is a useful control for ANOTHER case: A final review measures internal system uptime but never checks whether users can complete the core customer journey. The current situation is better prevented by: Require customer-visible acceptance measures in contracts.

C:

Include integration dependencies in release gate reviews. That is a useful control for ANOTHER case: A BA confirms that all backlog stories have a Done label but the release lacks the approved interface to a partner platform. The current situation is better prevented by: Require customer-visible acceptance measures in contracts.

D:

Include non-user oversight bodies in stakeholder mapping. That is a useful control for ANOTHER case: A regulator's reporting requirement affects an insurance application but product teams classify regulators as irrelevant because they cannot log into the app. The current situation is better prevented by: Require customer-visible acceptance measures in contracts.

Question 381

A CAPM-level project coordinator sees: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. What is the best next approved step?

  1. Treat the currently applicable standard as an enforceable scope and quality constraint.
  2. Consider a hybrid approach with fixed governance gates and iterative experimentation.
  3. Clarify authority to execute the preapproved response within agreed limits.
  4. Use a predictive baseline with controlled change and inspection points for defined construction deliverables.

Explanation

Correct Answer

D:

Use a predictive baseline with controlled change and inspection points for defined construction deliverables. This addresses the fictional case: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The project-management rationale is: Predictive planning suits comparatively stable, sequential and tightly regulated deliverables. Verify by: Authorized modifications appear in approved baseline revisions before field execution.

Incorrect Answers

A:

Treat the currently applicable standard as an enforceable scope and quality constraint. This would address a DIFFERENT fictional project situation: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. It is less directly applicable to: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes.

B:

Consider a hybrid approach with fixed governance gates and iterative experimentation. This would address a DIFFERENT fictional project situation: A research lab has a fixed compliance deadline but uncertain technical experiments and insists every activity must follow one lifecycle. It is less directly applicable to: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes.

C:

Clarify authority to execute the preapproved response within agreed limits. This would address a DIFFERENT fictional project situation: The risk owner identifies a trigger but refuses to act until the project manager attends the next meeting. It is less directly applicable to: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes.

Question 382

For an engineering consulting project, what is the strongest acceptance evidence after addressing: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes.

  1. Authorized modifications appear in approved baseline revisions before field execution.
  2. Independent evaluation records document a fair, reviewable procurement decision.
  3. The portfolio review compares competing investments and strategic alignment across distinct initiatives.
  4. Safety controls are implemented with incident evidence and stakeholder notification.

Explanation

Correct Answer

A:

Authorized modifications appear in approved baseline revisions before field execution. This validates the selected response: Use a predictive baseline with controlled change and inspection points for defined construction deliverables. The relevant management principle is: Predictive planning suits comparatively stable, sequential and tightly regulated deliverables.

Incorrect Answers

B:

Independent evaluation records document a fair, reviewable procurement decision. This is evidence for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The specific corrective response here is: Use a predictive baseline with controlled change and inspection points for defined construction deliverables.

C:

The portfolio review compares competing investments and strategic alignment across distinct initiatives. This is evidence for ANOTHER case: A university investment committee labels its unrelated campus construction and digital learning initiatives a single program. The specific corrective response here is: Use a predictive baseline with controlled change and inspection points for defined construction deliverables.

D:

Safety controls are implemented with incident evidence and stakeholder notification. This is evidence for ANOTHER case: An engineering project observes a new safety hazard but waits for its next monthly review despite an immediate-response risk trigger. The specific corrective response here is: Use a predictive baseline with controlled change and inspection points for defined construction deliverables.

Question 383

A postincident review considers: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. Which principle most directly accounts for the behavior?

  1. Adaptive approaches accommodate evolving requirements where detailed predictive baselines are unstable.
  2. Predictive planning suits comparatively stable, sequential and tightly regulated deliverables.
  3. Work grouping follows purpose and unique deliverables rather than mere shared staffing.
  4. Defined frameworks delegate preauthorized decisions to response owners.

Explanation

Correct Answer

B:

Predictive planning suits comparatively stable, sequential and tightly regulated deliverables. This explains the case: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The targeted action is: Use a predictive baseline with controlled change and inspection points for defined construction deliverables.

Incorrect Answers

A:

Adaptive approaches accommodate evolving requirements where detailed predictive baselines are unstable. This rationale better explains a DIFFERENT problem: A manufacturing team freezes all product details up front despite weekly regulatory discoveries that regularly change requirements. The key mechanism for the current situation is: Predictive planning suits comparatively stable, sequential and tightly regulated deliverables.

C:

Work grouping follows purpose and unique deliverables rather than mere shared staffing. This rationale better explains a DIFFERENT problem: A nonprofit calls a collection of separate volunteer events one project despite no shared end result or integrated scope. The key mechanism for the current situation is: Predictive planning suits comparatively stable, sequential and tightly regulated deliverables.

D:

Defined frameworks delegate preauthorized decisions to response owners. This rationale better explains a DIFFERENT problem: The risk owner identifies a trigger but refuses to act until the project manager attends the next meeting. The key mechanism for the current situation is: Predictive planning suits comparatively stable, sequential and tightly regulated deliverables.

Question 384

What ongoing preventive practice would most reduce recurrence of: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes.

  1. Include end-state ownership in facility-change proposals.
  2. Include a named receiving service owner in project definitions.
  3. Record the rationale for lifecycle selection at initiation.
  4. Document role and decision rights before portfolio review.

Explanation

Correct Answer

C:

Record the rationale for lifecycle selection at initiation. This helps prevent recurrence of: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The required evidence of effective control is: Authorized modifications appear in approved baseline revisions before field execution.

Incorrect Answers

A:

Include end-state ownership in facility-change proposals. That is a useful control for ANOTHER case: A temporary warehouse relocation has a defined final operating site, but managers treat it as routine daily warehousing. The current situation is better prevented by: Record the rationale for lifecycle selection at initiation.

B:

Include a named receiving service owner in project definitions. That is a useful control for ANOTHER case: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. The current situation is better prevented by: Record the rationale for lifecycle selection at initiation.

D:

Document role and decision rights before portfolio review. That is a useful control for ANOTHER case: A sponsor says a specific technician should decide which portfolio initiatives receive funding. The current situation is better prevented by: Record the rationale for lifecycle selection at initiation.

Question 385

At a nonprofit modernization team, the review identifies: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. Which response best addresses the specific project management problem?

  1. Record relevant stakeholder roles, interests, influence and planned engagement.
  2. Keep the supplier as an active stakeholder until their material work and influence end.
  3. Conduct formal acceptance, transition support ownership and complete closure documentation.
  4. Facilitate an estimation workshop that surfaces assumptions and reconciles work boundaries.

Explanation

Correct Answer

A:

Record relevant stakeholder roles, interests, influence and planned engagement. This addresses the fictional case: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The project-management rationale is: A stakeholder register enables deliberate engagement beyond a list of names. Verify by: The engagement plan identifies representatives and review contacts for patient impacts.

Incorrect Answers

B:

Keep the supplier as an active stakeholder until their material work and influence end. This would address a DIFFERENT fictional project situation: A project removes the supplier from its stakeholder register after contract signature even though supplier approval is needed for integration tests. It is less directly applicable to: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register.

C:

Conduct formal acceptance, transition support ownership and complete closure documentation. This would address a DIFFERENT fictional project situation: A completed ERP release has no acceptance record and the builders remain responsible for routine user support indefinitely. It is less directly applicable to: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register.

D:

Facilitate an estimation workshop that surfaces assumptions and reconciles work boundaries. This would address a DIFFERENT fictional project situation: A planning team asks employees to estimate a complex migration separately but then averages incompatible assumptions without discussion. It is less directly applicable to: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register.

Question 386

The project issue was: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. Which outcome demonstrates that its remedy worked?

  1. Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist.
  2. The engagement plan identifies representatives and review contacts for patient impacts.
  3. The revised resource plan assigns the required specialist during the dependent test window.
  4. The backup source begins after trigger evidence and restores planned delivery.

Explanation

Correct Answer

B:

The engagement plan identifies representatives and review contacts for patient impacts. This validates the selected response: Record relevant stakeholder roles, interests, influence and planned engagement. The relevant management principle is: A stakeholder register enables deliberate engagement beyond a list of names.

Incorrect Answers

A:

Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist. This is evidence for ANOTHER case: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. The specific corrective response here is: Record relevant stakeholder roles, interests, influence and planned engagement.

C:

The revised resource plan assigns the required specialist during the dependent test window. This is evidence for ANOTHER case: A remote migration is staffed with four developers although the schedule requires one specialized network reviewer unavailable that month. The specific corrective response here is: Record relevant stakeholder roles, interests, influence and planned engagement.

D:

The backup source begins after trigger evidence and restores planned delivery. This is evidence for ANOTHER case: A project team identifies a high-probability supplier delay but ignores its approved backup-source risk response. The specific corrective response here is: Record relevant stakeholder roles, interests, influence and planned engagement.

Question 387

For a nonprofit modernization team, the documented failure was: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. Which explanation is most accurate?

  1. Quality objectives need verifiable standards to guide assurance and acceptance.
  2. Clearly defined deliverables and quality criteria support controlled acceptance.
  3. A stakeholder register enables deliberate engagement beyond a list of names.
  4. High uncertainty makes learning and incremental validation valuable.

Explanation

Correct Answer

C:

A stakeholder register enables deliberate engagement beyond a list of names. This explains the case: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The targeted action is: Record relevant stakeholder roles, interests, influence and planned engagement.

Incorrect Answers

A:

Quality objectives need verifiable standards to guide assurance and acceptance. This rationale better explains a DIFFERENT problem: A quality plan specifies that software must be excellent but has no measurable tests. The key mechanism for the current situation is: A stakeholder register enables deliberate engagement beyond a list of names.

B:

Clearly defined deliverables and quality criteria support controlled acceptance. This rationale better explains a DIFFERENT problem: A project team approves a feature list but has no measurable criterion for accepting the final release. The key mechanism for the current situation is: A stakeholder register enables deliberate engagement beyond a list of names.

D:

High uncertainty makes learning and incremental validation valuable. This rationale better explains a DIFFERENT problem: A market-testing initiative keeps an immutable specification after customer interviews reveal the solution solves the wrong need. The key mechanism for the current situation is: A stakeholder register enables deliberate engagement beyond a list of names.

Question 388

Which recurring governance check best addresses the risk of repeating: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register.

  1. Include environment capacity in the integrated schedule.
  2. Require transition-ready documentation before final closure.
  3. Include decision limits and trigger tests in risk playbooks.
  4. Revalidate stakeholder records after organizational changes.

Explanation

Correct Answer

D:

Revalidate stakeholder records after organizational changes. This helps prevent recurrence of: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The required evidence of effective control is: The engagement plan identifies representatives and review contacts for patient impacts.

Incorrect Answers

A:

Include environment capacity in the integrated schedule. That is a useful control for ANOTHER case: An offshore development team plans 12 parallel testing activities on one shared lab environment. The current situation is better prevented by: Revalidate stakeholder records after organizational changes.

B:

Require transition-ready documentation before final closure. That is a useful control for ANOTHER case: A completed ERP release has no acceptance record and the builders remain responsible for routine user support indefinitely. The current situation is better prevented by: Revalidate stakeholder records after organizational changes.

C:

Include decision limits and trigger tests in risk playbooks. That is a useful control for ANOTHER case: The risk owner identifies a trigger but refuses to act until the project manager attends the next meeting. The current situation is better prevented by: Revalidate stakeholder records after organizational changes.

Question 389

During a project review, stakeholders report: A specialist developer is responsible for test code but is treated as the person who approves project strategy. What should the team do first?

  1. Communicate evidence and assumptions early while offering constructive response options.
  2. Assign technical delivery accountability to the team and strategy authorization to governance roles.
  3. Facilitate a two-way discussion and obtain confirmation of shared meaning.
  4. Revise the proposed scope through authorized agreement to include acceptance and training deliverables.

Explanation

Correct Answer

B:

Assign technical delivery accountability to the team and strategy authorization to governance roles. This addresses the fictional case: A specialist developer is responsible for test code but is treated as the person who approves project strategy. The project-management rationale is: Team members produce work; governance roles approve strategic direction. Verify by: Responsibility mapping matches decisions to role authority and expertise.

Incorrect Answers

A:

Communicate evidence and assumptions early while offering constructive response options. This would address a DIFFERENT fictional project situation: A junior PM withholds forecast problems because they believe leadership means never admitting uncertainty. It is less directly applicable to: A specialist developer is responsible for test code but is treated as the person who approves project strategy.

C:

Facilitate a two-way discussion and obtain confirmation of shared meaning. This would address a DIFFERENT fictional project situation: A remote team cannot resolve a misunderstanding because instructions are sent only as one-way technical memos. It is less directly applicable to: A specialist developer is responsible for test code but is treated as the person who approves project strategy.

D:

Revise the proposed scope through authorized agreement to include acceptance and training deliverables. This would address a DIFFERENT fictional project situation: A sponsor promises a mobile app and training but the scope statement lists only application coding. It is less directly applicable to: A specialist developer is responsible for test code but is treated as the person who approves project strategy.

Question 390

Following the proposed correction, what observation confirms success: A specialist developer is responsible for test code but is treated as the person who approves project strategy.

  1. Experts confirm that the documented constraints reflect their input.
  2. Both sides accept a documented solution without an unresolved relationship complaint.
  3. Responsibility mapping matches decisions to role authority and expertise.
  4. The evaluation record shows fair application of approved criteria with no confidential disclosure.

Explanation

Correct Answer

C:

Responsibility mapping matches decisions to role authority and expertise. This validates the selected response: Assign technical delivery accountability to the team and strategy authorization to governance roles. The relevant management principle is: Team members produce work; governance roles approve strategic direction.

Incorrect Answers

A:

Experts confirm that the documented constraints reflect their input. This is evidence for ANOTHER case: An inexperienced coordinator repeatedly interrupts senior subject experts and misses material project constraints. The specific corrective response here is: Assign technical delivery accountability to the team and strategy authorization to governance roles.

B:

Both sides accept a documented solution without an unresolved relationship complaint. This is evidence for ANOTHER case: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides. The specific corrective response here is: Assign technical delivery accountability to the team and strategy authorization to governance roles.

D:

The evaluation record shows fair application of approved criteria with no confidential disclosure. This is evidence for ANOTHER case: A procurement manager requests a hidden bid advantage from a supplier in exchange for confidential evaluation scores. The specific corrective response here is: Assign technical delivery accountability to the team and strategy authorization to governance roles.