Question 330
How should the project team verify a successful response to: An engineering project has earned value $75,000 and planned value $60,000 but staff report 15,000 dollars behind schedule.
Explanation
Correct Answer
The reconciled status report interprets positive SV correctly. This validates the selected response: Compute EV−PV and report the positive $15,000 schedule variance. The relevant management principle is: Positive SV means earned progress exceeds the plan's earned-value target at that date.
Incorrect Answers
The forecasted duration matches the network's valid 14-day critical path. This is evidence for ANOTHER case: A dependency graph shows two parallel work paths of 14 and 11 days, and the team adds both to forecast a 25-day project. The specific corrective response here is: Compute EV−PV and report the positive $15,000 schedule variance.
The WBS lists design, fit-out, integration, testing and handover outputs. This is evidence for ANOTHER case: A plan uses one undifferentiated task called build hospital with no deliverable ownership or progress measure. The specific corrective response here is: Compute EV−PV and report the positive $15,000 schedule variance.
Each component has an appropriate owner, input, acceptance test and handoff date. This is evidence for ANOTHER case: A project lists stakeholder acceptance and maintenance training as tasks inside design engineering without distinct owners. The specific corrective response here is: Compute EV−PV and report the positive $15,000 schedule variance.