Question 280
For the previous project issue, select the best preventive control: Developers build every backlog request from one stakeholder without verifying whether it serves the approved product goal.
Explanation
Correct Answer
Review objective alignment during iteration planning. This helps prevent recurrence of: Developers build every backlog request from one stakeholder without verifying whether it serves the approved product goal. The required evidence of effective control is: Completed stories can be traced to the agreed value objective.
Incorrect Answers
Audit metric incentives and changes to story boundaries. That is a useful control for ANOTHER case: A team repeatedly splits stories after sprint completion to make velocity reports look favorable. The current situation is better prevented by: Review objective alignment during iteration planning.
Review material risk as part of regular backlog refinement. That is a useful control for ANOTHER case: A product owner ranks bug fixes only by how many users complained, ignoring a low-volume critical security vulnerability. The current situation is better prevented by: Review objective alignment during iteration planning.
Reconcile shared dependencies at regular integration reviews. That is a useful control for ANOTHER case: A multi-site project has separate sprint boards that cannot show one shared release objective or integration issue. The current situation is better prevented by: Review objective alignment during iteration planning.