Question 250
How should the project team verify a successful response to: A planning coordinator includes routine daily customer support as the completion deliverable for a time-limited database migration.
Explanation
Correct Answer
The work breakdown shows migration outputs and operating handoff without claiming indefinite support as project work. This validates the selected response: Separate operational service delivery from the migration's product, scope and transition components. The relevant management principle is: A project's component deliverables are finite while ongoing operations continue afterward.
Incorrect Answers
Project schedules and functional work calendars reflect the same approved commitment. This is evidence for ANOTHER case: A functional department loans staff to a project without acknowledging the project's fixed schedule responsibilities. The specific corrective response here is: Separate operational service delivery from the migration's product, scope and transition components.
The activation cannot begin until verified commissioning acceptance is recorded. This is evidence for ANOTHER case: A transit modernization project combines commissioning tests and public activation into one work package despite mandatory test signoff. The specific corrective response here is: Separate operational service delivery from the migration's product, scope and transition components.
The network shows no finish-date improvement when only the noncritical task changes. This is evidence for ANOTHER case: A project network has multiple paths with a 20-day maximum path, but the team accelerates a noncritical five-day activity and expects an earlier completion. The specific corrective response here is: Separate operational service delivery from the migration's product, scope and transition components.