Question 200
For the previous project issue, select the best preventive control: An XP team avoids automated tests and refactoring because leaders believe continuous integration is sufficient.
Explanation
Correct Answer
Track test quality and technical debt in retrospectives. This helps prevent recurrence of: An XP team avoids automated tests and refactoring because leaders believe continuous integration is sufficient. The required evidence of effective control is: Changes pass repeatable tests and code remains maintainable.
Incorrect Answers
Revisit state policies when bottlenecks recur. That is a useful control for ANOTHER case: A Kanban board contains no explicit entry or completion rules and stakeholders disagree on what In Review means. The current situation is better prevented by: Track test quality and technical debt in retrospectives.
Tailor method to demand and delivery characteristics. That is a useful control for ANOTHER case: A manager orders every team to run fixed-length sprints even though one support service has unpredictable continuous ticket arrivals. The current situation is better prevented by: Track test quality and technical debt in retrospectives.
Apply lightweight readiness criteria before selection. That is a useful control for ANOTHER case: A team estimates a story as small yet repeatedly discovers hidden dependencies after sprint commitment. The current situation is better prevented by: Track test quality and technical debt in retrospectives.