Question 130
The project issue was: A bank's product manager defines long-term market positioning but a team expects them to prioritize every daily sprint item without a product owner. Which outcome demonstrates that its remedy worked?
Explanation
Correct Answer
Strategic roadmap and iteration backlog each have clearly accountable decision makers. This validates the selected response: Distinguish product strategy and management from the delegated product-backlog prioritization role. The relevant management principle is: Product managers and product owners may have distinct strategy versus tactical prioritization responsibilities.
Incorrect Answers
The requirements engagement plan includes the supplier's necessary interface approvals. This is evidence for ANOTHER case: A supplier representative influences integration requirements but is excluded from the stakeholder list because they are external. The specific corrective response here is: Distinguish product strategy and management from the delegated product-backlog prioritization role.
Unresolved acceptance conflicts reach accountable business governance with delivery impact analysis. This is evidence for ANOTHER case: A team treats a business sponsor and the delivery PM as interchangeable when resolving conflicting product acceptance goals. The specific corrective response here is: Distinguish product strategy and management from the delegated product-backlog prioritization role.
App increments deploy only when the required infrastructure capability is verified. This is evidence for ANOTHER case: A multi-phase modernization uses predictive infrastructure acquisition and agile app delivery but the analyst ignores the dependency between them. The specific corrective response here is: Distinguish product strategy and management from the delegated product-backlog prioritization role.