Question 460
After remediation, an administrator is asked to prevent recurrence of: A company sets a target to finish every impact assessment but provides no people or budget. What practice belongs in the runbook?
Explanation
Correct Answer
The lasting control is: Review budget and competence assumptions when setting future AIMS objectives. It addresses recurrence of this mechanism: The objective plan omits necessary resources and a feasible delivery approach. A successful system should still demonstrate: Resourcing and assessment completion evidence support progress against the target.
Incorrect Answers
This control would require a measurable success plan for every approved AIMS objective; it responds to the risk in which an AI-policy objective says algorithms will be trustworthy but has no indicators or review timing. It would not address the current root cause: the objective plan omits necessary resources and a feasible delivery approach.
The failure in the question arises because the objective plan omits necessary resources and a feasible delivery approach. A safeguard to schedule objective review after all material AIMS boundary changes serves situations where a program's AI objective remains unchanged after management withdraws the underlying high-risk service rather than this one.
The proposed check would require monitored outcomes before closing objective-related project work, helping with cases where an AI risk committee records a quantitative target but never reviews its result after release. The recurring exposure described here is that the objective plan omits necessary resources and a feasible delivery approach.