Question 370
The organization has addressed this management-system failure: A project milestone says complete governance without specifying verifiable deliverables. Which verification finding supports closure?
Explanation
Correct Answer
The strongest confirmation is: The steering group can accept deliverables against predetermined proof criteria. It is evidence for the specific corrective step—Define each deliverable, owner, evidence artifact and acceptance standard for the milestone.—rather than a generic system-health signal.
Incorrect Answers
Even if this observation were recorded, it would support a case where a bank measures project completion only by the number of policies written. It would not verify that the steering group can accept deliverables against predetermined proof criteria.
The result would be meaningful for a problem where a team launches all AI governance changes simultaneously across high-risk operational services. For this question, closure depends on confirming that the steering group can accept deliverables against predetermined proof criteria.
The result would be meaningful for a problem where a project manager delegates the risk methodology to a vendor but leaves no internal approval authority. For this question, closure depends on confirming that the steering group can accept deliverables against predetermined proof criteria.