Question 30
A dataflow refresh is triggered as part of a nightly pipeline but must finish before downstream notebook processing. Which engineering decision is most suitable for this specific situation?
Explanation
Correct Answer
Explicit dependencies prevent processing before upstream dataflow completion.
Incorrect Answers
Pipelines orchestrate multi-activity ingestion and dependent jobs.
Child pipelines allow shared orchestration logic without cloning all activities.
Parallel branches enable independent work once common prerequisites are met.