Question 640
Following a branch infrastructure consolidation project, Copper Hill Studios claims its remediation succeeded: Engineers size destination Azure VMs solely from configured on-premises CPU and RAM without considering real usage. Which result is the STRONGEST independent acceptance evidence?
Explanation
Correct Answer
Recommendations reflect measured load and pass the approved cost and performance review. This directly verifies the reported failure: Engineers size destination Azure VMs solely from configured on-premises CPU and RAM without considering real usage. It demonstrates that the corrective action—Use performance-based Azure Migrate assessment with an appropriate data collection period—worked for Copper Hill Studios. A completion ticket or configuration claim alone would not prove that outcome.
Incorrect Answers
A postmigration benchmark meets required IOPS and latency without saturation. This is acceptance evidence for a different condition: A high-I/O database virtual machine is moved to an Azure disk tier that cannot sustain its measured throughput, ordinarily addressed by Use workload-specific migration assessment to choose supported disk performance tiers and sizes. It does not establish that Copper Hill Studios resolved the observed problem. The decisive result would be: Recommendations reflect measured load and pass the approved cost and performance review.
A pilot user authenticates and completes the application's business transaction from Azure. This is acceptance evidence for a different condition: An Azure Migrate pilot reports success despite application authentication failing against a directory that remained on-premises, ordinarily addressed by Validate hybrid connectivity, domain access and identity dependencies during test migration. It does not establish that Copper Hill Studios resolved the observed problem. The decisive result would be: Recommendations reflect measured load and pass the approved cost and performance review.
The target starts at the chosen recovery point with measured downtime within the approved window. This is acceptance evidence for a different condition: The initial replication is healthy but final migration is launched during a peak load period with a large unsynchronized delta, ordinarily addressed by Schedule cutover based on replication progress, maintenance constraints and application-consistent shutdown. It does not establish that Copper Hill Studios resolved the observed problem. The decisive result would be: Recommendations reflect measured load and pass the approved cost and performance review.