Question 40
An Azure VM cannot be resized to a selected SKU while running, and the portal indicates the change requires deallocation. What is the next appropriate administrative step after scheduling downtime?
Explanation
Correct Answer
Deallocation releases allocated compute resources and allows supported changes that cannot occur on the running host. The selected SKU must be available in the target region/cluster.
Incorrect Answers
An in-guest restart does not release the VM allocation. The scenario requires Azure stop/deallocate before selecting an available size.
Disk performance and VM compute size are separately configured. A VM resize may require deallocation and available capacity.
ReadOnly locks block management writes and cannot make a resize succeed. The required next step is deallocation and a supported SKU.