Question 380
At a government annex, an issue has been corrected: A site-level Marvis Action indicates repeated DHCP failures but the NOC dismisses it after fixing one unrelated AP. Which repeatable control should the team add to prevent it from returning?
Explanation
Correct Answer
Investigate affected client populations before closing Marvis Actions. This repeatable safeguard addresses the mechanism—a site-scoped action may describe a common service dependency rather than a single failed AP—and reduces the chance that the specific fault recurs.
Incorrect Answers
Define action-specific automation eligibility, permission and rollback requirements. This protects against another issue—a technician sees a Marvis Action that can be self-remediated and assumes all action classes permit autonomous configuration without permissions or policy—but is not the most direct prevention for a site-level Marvis Action indicates repeated DHCP failures but the NOC dismisses it after fixing one unrelated AP.
Review evidence sources before selecting corrective WLAN actions from Marvis responses. This protects against another issue—a support engineer accepts a Marvis response suggesting an authentication problem but immediately changes RRM transmit power—but is not the most direct prevention for a site-level Marvis Action indicates repeated DHCP failures but the NOC dismisses it after fixing one unrelated AP.
Triages Marvis Actions at both organization and site scopes. This protects against another issue—the organization reviews only global Marvis Actions and misses a severe recurring WLAN issue limited to one branch—but is not the most direct prevention for a site-level Marvis Action indicates repeated DHCP failures but the NOC dismisses it after fixing one unrelated AP.