Question 120
After a targeted improvement affecting booking and traveler notifications, the customer success team at a travel platform in Madrid examines the original concern: a service design assumes outsourced identity-provider commitments are under direct internal control. What measurable result shows the problem has been addressed?
Explanation
Correct Answer
Correct. For the Partners and suppliers issue at a travel platform in Madrid, the expected action is: Address third-party dependencies, commercial relationships, and supplier capabilities. This observation directly checks the intended result: The team has supplier assurance and agreed responsibilities for external dependencies. It is tied to the original failure rather than a generic activity measure.
Incorrect Answers
This observation is evidence for holistic approach: The business case covers people, technology, external relationships, and processes. That would be relevant to a separate problem where an IT improvement installs new software while ignoring suppliers, personnel, and workflow effects. The a travel platform in Madrid case instead needs evidence that The team has supplier assurance and agreed responsibilities for external dependencies; the offered observation would not establish that outcome.
This observation is evidence for supplier resilience: Supplier monitoring and continuity agreements match the downstream service risk. That would be relevant to a separate problem where an organization relies on a single API supplier with no understanding of outage commitments. The a travel platform in Madrid case instead needs evidence that The team has supplier assurance and agreed responsibilities for external dependencies; the offered observation would not establish that outcome.
This observation is evidence for governance of roles: Every response step has an owner and teams can escalate without ambiguity. That would be relevant to a separate problem where an operations team has no clear accountable owner for shared incident response decisions. The a travel platform in Madrid case instead needs evidence that The team has supplier assurance and agreed responsibilities for external dependencies; the offered observation would not establish that outcome.