Question 750
During a release-readiness review, a tester observes: A project manager uses a three-point estimate optimistic 2 days, most likely 5 days, pessimistic 11 days, but reports a simple arithmetic mean without stating the chosen formula. Which observation best verifies that the stated testing issue is addressed?
Explanation
Correct Answer
This is the expected verification outcome: The weighted estimate is 5.5 days with its formula and assumptions documented. It directly checks the corrective activity (If using PERT, apply (optimistic + 4×most likely + pessimistic)/6 to these assumptions.) for the described testing problem.
Incorrect Answers
This result may validate another testing scenario: An online retailer has only one day of test execution left but tries to run the full lower-risk suite before high-priority payment cases because the full suite is easier to schedule. It does not establish the required result for this case: The weighted estimate is 5.5 days with its formula and assumptions documented.
This result may validate another testing scenario: A new feature has ten low-risk cosmetic tests and three critical authorization tests, but the tester executes the cosmetic tests first because they are shorter. It does not establish the required result for this case: The weighted estimate is 5.5 days with its formula and assumptions documented.
This result may validate another testing scenario: A bank restores a failed staging environment from a snapshot but cannot determine which database schema, service version and configuration were present before restoration. It does not establish the required result for this case: The weighted estimate is 5.5 days with its formula and assumptions documented.