Question 800
Fictional Summit Gate Production is completing a requirements and current-capability comparison with plant engineering and operations personnel. During a design assurance checkpoint, the case presents this industrial security assessment concern: A pumping station relies on a single data link for control telemetry and maintenance downloads without defining capacity reserve or overload behavior. The team must prioritize safe operation, authorized assessment methods, and evidence from the actual process environment. Which repeatable governance check should keep the assessment finding current?
Explanation
Correct Answer
Revalidate overload controls as telemetry rates, remote clients, and carrier services change. That recurring check targets the underlying weakness: security-related availability includes preserving critical functions when less important communications compete for constrained resources.
Incorrect Answers
Tie controller additions and cabinet modifications to asset-register updates and periodic reconciliation. Unlisted control assets cannot be evaluated for credible exposure, supportability, or consequences simply by counting servers. The relevant follow-up is: Revalidate overload controls as telemetry rates, remote clients, and carrier services change.
Require device-specific safe-discovery approval whenever assessment tools or control hardware change. Industrial devices may react unpredictably to unexpected traffic even when conventional IT scanners consider probes nonintrusive. The relevant follow-up is: Revalidate overload controls as telemetry rates, remote clients, and carrier services change.
Reassess capture coverage after network redesign, controller redundancy changes, and new segmented links. Passive collection cannot prove absence of a vulnerability on network paths it never monitored. The relevant follow-up is: Revalidate overload controls as telemetry rates, remote clients, and carrier services change.