Question 670
Fictional Harborview Engineering Plant is completing an industrial zone and boundary review with plant engineering and operations personnel. During a process upset tabletop, the case presents this industrial security assessment concern: A newly built refinery includes an unrestricted link between engineering and process zones to speed startup tests, and the link remains after production release. The team must prioritize safe operation, authorized assessment methods, and evidence from the actual process environment. What ongoing verification best prevents the specific gap from returning?
Explanation
Correct Answer
Audit temporary conduit expiry and closure before every commissioning-to-operations transfer. It helps maintain the control because temporary functional convenience often creates a lasting security pathway unless exception closure is treated as a formal deliverable.
Incorrect Answers
Tie controller additions and cabinet modifications to asset-register updates and periodic reconciliation. Unlisted control assets cannot be evaluated for credible exposure, supportability, or consequences simply by counting servers. To reduce recurrence in this case, audit temporary conduit expiry and closure before every commissioning-to-operations transfer.
Require device-specific safe-discovery approval whenever assessment tools or control hardware change. Industrial devices may react unpredictably to unexpected traffic even when conventional IT scanners consider probes nonintrusive. To reduce recurrence in this case, audit temporary conduit expiry and closure before every commissioning-to-operations transfer.
Reassess capture coverage after network redesign, controller redundancy changes, and new segmented links. Passive collection cannot prove absence of a vulnerability on network paths it never monitored. To reduce recurrence in this case, audit temporary conduit expiry and closure before every commissioning-to-operations transfer.