Question 230
Fictional Northshore Plant Operations is completing a process safety and cyber dependency review with plant engineering and operations personnel. During an operator-led risk workshop, the case presents this industrial security assessment concern: An industrial water operator marks a display-server outage as identical to the loss of closed-loop control, despite controllers being able to continue locally. The team must prioritize safe operation, authorized assessment methods, and evidence from the actual process environment. Which repeatable governance check should keep the assessment finding current?
Explanation
Correct Answer
Reassess operational visibility dependencies after HMI, alarming, or controller autonomy changes. Human supervisory functions and local automatic control may fail differently, producing different consequences and response times.
Incorrect Answers
Tie controller additions and cabinet modifications to asset-register updates and periodic reconciliation. Unlisted control assets cannot be evaluated for credible exposure, supportability, or consequences simply by counting servers. The recurring safeguard for this issue is: Reassess operational visibility dependencies after HMI, alarming, or controller autonomy changes.
Reconcile I/O communication maps after cabinet expansion and network switch replacement. Distributed I/O is part of the operational control function even when no operator logs directly into the remote rack. The recurring safeguard for this issue is: Reassess operational visibility dependencies after HMI, alarming, or controller autonomy changes.
Update the commissioning assessment checklist when construction phases or integration contractors introduce new service paths. Short-lived project access may carry privileged functions even though it will not exist in the final operational network diagram. The recurring safeguard for this issue is: Reassess operational visibility dependencies after HMI, alarming, or controller autonomy changes.