Question 200
A technical assessment of Summit City Transit's fare collection and vehicle location reporting documents this issue: A warehouse cutover is approved without a rollback plan or reconciliation of historical financial balances. The implementation team reports the corrective work finished. Which observation BEST demonstrates that the original problem has been resolved?
Explanation
Correct Answer
Parallel reports reconcile and an injected failure triggers the preagreed rollback procedure. This measurable result directly tests the chosen correction (Stage migration rehearsals, parallel run validation and rollback criteria before production cutover) against the initial failure (A warehouse cutover is approved without a rollback plan or reconciliation of historical financial balances). For Summit City Transit's fare collection and vehicle location reporting, validated operational evidence is stronger than an untested completion ticket.
Incorrect Answers
Migration plan maps each critical object and dependent consumer to a tested target implementation. That measurement belongs to another cause (A legacy Oracle warehouse has no migration inventory and planners guess object compatibility before moving to BigQuery) after the different mitigation (Inventory source schemas query patterns workloads and transformation dependencies before designing the migration). It does not prove that the required outcome for Summit City Transit's fare collection and vehicle location reporting occurred: Parallel reports reconcile and an injected failure triggers the preagreed rollback procedure.
Test archive lands with preserved file checksums and no unnecessary database replication jobs. That measurement belongs to another cause (Database Migration Service is selected for a one-time static object archive without evaluating service fit) after the different mitigation (Select a suitable Cloud Storage transfer pathway for static files and reserve database migration tools for supported database moves). It does not prove that the required outcome for Summit City Transit's fare collection and vehicle location reporting occurred: Parallel reports reconcile and an injected failure triggers the preagreed rollback procedure.
Boundary-day transactions reconcile to the same audited business date after the migration. That measurement belongs to another cause (A migration loads a decade of data but source timezone conversion changes daily financial rollups) after the different mitigation (Define explicit timestamp normalization and timezone-preserving test cases for historical conversion). It does not prove that the required outcome for Summit City Transit's fare collection and vehicle location reporting occurred: Parallel reports reconcile and an injected failure triggers the preagreed rollback procedure.