Question 550
Before promoting an environment into production, operations must finish two tasks. Each requirement refers to its own target workload. Requirement A: a public HTTPS website needs URL path routing to distinct backends. Requirement B: a large datacenter needs dedicated physical connectivity to Google Cloud. Which ordered pair gives an appropriate answer for task one, then task two?
Explanation
Correct Answer
Application Load Balancers operate at HTTP Layer 7. Dedicated Interconnect provides physical private connectivity options.
Incorrect Answers
The second action is valid: Dedicated Interconnect provides physical private connectivity options. But the first fails: Passthrough network load balancing does not parse HTTP URL paths.
Both requirements remain unmet: Passthrough network load balancing does not parse HTTP URL paths; DNS records are not physical network circuits.