Question 540
An analyst plans the following FortiAnalyzer response: Reschedule heavy reports to off-peak intervals and avoid simultaneous log maintenance operations. Which original investigation or operational requirement is best matched to that response?
Explanation
Correct Answer
Spacing report jobs reduces resource contention with ingestion and database processing during busy hours. This directly addresses the scenario through report off-peak performance.
Incorrect Answers
Report scope settings determine which devices' data contributes to the generated statistics. That choice concerns report device scope restriction rather than the requested report off-peak performance.
Report attachments retain analytical context alongside incident findings rather than leaving the case without its supporting summary. That choice concerns report-generated incident evidence rather than the requested report off-peak performance.
Report scheduling automates generation at a defined cadence once the data and report settings are in place. That choice concerns scheduled recurring report rather than the requested report off-peak performance.