Question 830
A server operations team encounters the following situation: A manufacturing operation needs recovery within minutes, but its disaster recovery plan specifies an empty cold site with no preinstalled servers. After making the corrective change, which result best demonstrates that this particular problem is resolved?
Explanation
Correct Answer
This is incident-specific acceptance evidence: A realistic relocation drill resumes critical production within the target window. It verifies the action choose a suitably provisioned warm or hot recovery arrangement that meets the tested RTO. The failure under test was: A cold site entails equipment provisioning time inconsistent with short recovery demands.
Incorrect Answers
This observation tests an unrelated Explain the importance of disaster recovery case: Two supposedly independent recovery sites share the same local floodplain and utility substation, putting both at risk in one event. It may be true while the current failure persists; the decisive current cause is: A cold site entails equipment provisioning time inconsistent with short recovery demands.
This observation tests an unrelated Explain the importance of disaster recovery case: A geographically remote recovery database is asynchronous but monitors only connection uptime, overlooking hours of growing replication lag. It may be true while the current failure persists; the decisive current cause is: A cold site entails equipment provisioning time inconsistent with short recovery demands.
This observation tests an unrelated Explain the importance of disaster recovery case: An incident plan claims the cloud is always available during a regional outage but deploys all backup VMs and storage in one cloud region. It may be true while the current failure persists; the decisive current cause is: A cold site entails equipment provisioning time inconsistent with short recovery demands.