Question 380
An industrial plant needs a diagram of enterprise, supervisory, and process-control zones. Which result shows the selected action was suitable and effective?
Explanation
Correct Answer
The design maps IT and process-control assets to appropriate levels. This answer directly addresses the described constraint. Purdue levels organize industrial control network functions and boundaries. Successful validation requires: The design maps IT and process-control assets to appropriate levels.
Incorrect Answers
That approach concerns a different situation: a web application team wants a prioritized list of common application security risk categories. OWASP Top 10 groups frequent web application security risks. The required result is that the design maps IT and process-control assets to appropriate levels. The relevant evidence is: The design maps IT and process-control assets to appropriate levels.
It would address a tester needs a structured penetration testing workflow from pre-engagement to reporting. The relevant reason in that case is: PTES explicitly addresses preparation, discovery, exploitation, and reporting. Here the required success condition is the design maps IT and process-control assets to appropriate levels. The relevant evidence is: The design maps IT and process-control assets to appropriate levels.
This result applies to a different case: A SOC wants observed adversary behavior mapped to detection technique identifiers. ATT&CK classifies adversary behavior rather than providing a full test contract. It does not establish the present requirement, where the design maps IT and process-control assets to appropriate levels. The relevant evidence is: The design maps IT and process-control assets to appropriate levels.