Question 940
At Silver Cove Payments, the delivery assessment finds: Quality measurements fluctuate within expected common-cause limits but managers treat every single data point as an emergency. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The review identifies signals outside expected limits instead of reacting to normal noise. This is the relevant acceptance evidence because it tests whether the corrective action (Use a control chart with appropriately derived control limits to distinguish exceptional variation.) fixed the original concern (Quality measurements fluctuate within expected common-cause limits but managers treat every single data point as an emergency.) at Silver Cove Payments, rather than relying only on a task marked complete. The affected work concerns transaction data and fraud monitoring.
Incorrect Answers
The forecast uses the team's measured trend rather than treating cross-team points as equivalent. This evidence would be useful for another condition (The Scrum team cannot judge delivery capacity because it compares different story-point definitions from unrelated teams.) and its different action (Track velocity within the same stable team and estimation approach across iterations.). At Silver Cove Payments, it does not demonstrate the required project outcome: The review identifies signals outside expected limits instead of reacting to normal noise.
The estimate and assumptions can be independently recomputed from the three inputs. This evidence would be useful for another condition (The sponsor asks how many days a project will take but the estimate has best likely and worst cases with unequal plausibility.) and its different action (Use three-point PERT reasoning to calculate and communicate a weighted expected duration.). At Silver Cove Payments, it does not demonstrate the required project outcome: The review identifies signals outside expected limits instead of reacting to normal noise.
The chart reveals dominant categories and enables a focused improvement decision. This evidence would be useful for another condition (A release has many defect categories and the quality lead cannot tell which few causes produce most rework.) and its different action (Use a Pareto chart to rank defect categories by frequency or impact.). At Silver Cove Payments, it does not demonstrate the required project outcome: The review identifies signals outside expected limits instead of reacting to normal noise.