Question 820
Harbor Point Medical is delivering an IT initiative involving clinical collaboration and patient information with several affected stakeholder groups. The team observes: Leadership wants to see how much scope has been delivered while total product scope has grown during the iteration. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The chart separates progress on delivered work from additions to overall scope. This is the relevant acceptance evidence because it tests whether the corrective action (Use a burnup chart showing completed work against the changing total-scope line.) fixed the original concern (Leadership wants to see how much scope has been delivered while total product scope has grown during the iteration.) at Harbor Point Medical, rather than relying only on a task marked complete. The affected work concerns clinical collaboration and patient information.
Incorrect Answers
The sponsor can identify start finish and overlap of work on the approved time axis. This evidence would be useful for another condition (A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list.) and its different action (Build a Gantt chart from scheduled tasks dependencies and milestones.). At Harbor Point Medical, it does not demonstrate the required project outcome: The chart separates progress on delivered work from additions to overall scope.
The chart shows actual remaining work and makes deviations from the ideal trend visible. This evidence would be useful for another condition (An Agile release is halfway through but the team cannot forecast remaining work because it records only total stories ever completed.) and its different action (Use a burndown chart comparing remaining planned work with sprint time.). At Harbor Point Medical, it does not demonstrate the required project outcome: The chart separates progress on delivered work from additions to overall scope.
A selected scope change has one traceable decision and closure record. This evidence would be useful for another condition (A project manager needs a formal record of proposed scope modifications but stores change requests as unrelated emails.) and its different action (Maintain a controlled change log with identifiers impacts approvals and implementation status.). At Harbor Point Medical, it does not demonstrate the required project outcome: The chart separates progress on delivered work from additions to overall scope.