Question 700
For Eastport Research Hospital, the business analyst reports the following delivery problem: Senior management asks for sprint progress but the team reports only hours spent and not delivered accepted work. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The progress dashboard differentiates accepted functionality from unfinished in-progress tasks. This is the relevant acceptance evidence because it tests whether the corrective action (Report completed deliverables and relevant quality outcomes alongside effort and velocity.) fixed the original concern (Senior management asks for sprint progress but the team reports only hours spent and not delivered accepted work.) at Eastport Research Hospital, rather than relying only on a task marked complete. The affected work concerns medical research systems and directory accounts.
Incorrect Answers
The current status report shows completed activities and quantified variances from authorized work. This evidence would be useful for another condition (A team is executing a project but daily work is selected outside the approved project plan with no variance reporting.) and its different action (Direct execution using approved tasks and track actual progress against baselines.). At Eastport Research Hospital, it does not demonstrate the required project outcome: The progress dashboard differentiates accepted functionality from unfinished in-progress tasks.
The monthly forecast shows committed spend and remaining cost-to-complete transparently. This evidence would be useful for another condition (A project discovers a cost overrun but finance reports retain the original estimate as if no actual spend occurred.) and its different action (Update the project budget forecast with actual expenditures and documented corrective actions.). At Eastport Research Hospital, it does not demonstrate the required project outcome: The progress dashboard differentiates accepted functionality from unfinished in-progress tasks.
The sponsor receives traceable milestone risk budget and issue data by the reporting deadline. This evidence would be useful for another condition (A project manager sends only ad hoc verbal updates while the steering committee requires an accountable monthly risk and progress report.) and its different action (Use the approved reporting cadence and publish a documented project status update.). At Eastport Research Hospital, it does not demonstrate the required project outcome: The progress dashboard differentiates accepted functionality from unfinished in-progress tasks.