Question 650
At Harbor Point Medical, the delivery assessment finds: A critical integration task slips by ten days but the PM sends a green schedule report using last month's dates. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The schedule report identifies the slip affected milestones and recovery decision. This is the relevant acceptance evidence because it tests whether the corrective action (Update the timeline forecast and communicate the actual dependency impact.) fixed the original concern (A critical integration task slips by ten days but the PM sends a green schedule report using last month's dates.) at Harbor Point Medical, rather than relying only on a task marked complete. The affected work concerns clinical collaboration and patient information.
Incorrect Answers
The monthly forecast shows committed spend and remaining cost-to-complete transparently. This evidence would be useful for another condition (A project discovers a cost overrun but finance reports retain the original estimate as if no actual spend occurred.) and its different action (Update the project budget forecast with actual expenditures and documented corrective actions.). At Harbor Point Medical, it does not demonstrate the required project outcome: The schedule report identifies the slip affected milestones and recovery decision.
The current status report shows completed activities and quantified variances from authorized work. This evidence would be useful for another condition (A team is executing a project but daily work is selected outside the approved project plan with no variance reporting.) and its different action (Direct execution using approved tasks and track actual progress against baselines.). At Harbor Point Medical, it does not demonstrate the required project outcome: The schedule report identifies the slip affected milestones and recovery decision.
The sponsor receives traceable milestone risk budget and issue data by the reporting deadline. This evidence would be useful for another condition (A project manager sends only ad hoc verbal updates while the steering committee requires an accountable monthly risk and progress report.) and its different action (Use the approved reporting cadence and publish a documented project status update.). At Harbor Point Medical, it does not demonstrate the required project outcome: The schedule report identifies the slip affected milestones and recovery decision.