Question 570
At Evergreen Hospital, the delivery assessment finds: A new service will go live but service-desk training and operational ownership are absent from the project plan. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
An operations representative completes the handoff checklist and accepts ownership. This is the relevant acceptance evidence because it tests whether the corrective action (Prepare a transition plan covering operational readiness knowledge transfer training and handoff.) fixed the original concern (A new service will go live but service-desk training and operational ownership are absent from the project plan.) at Evergreen Hospital, rather than relying only on a task marked complete. The affected work concerns care coordination and staff identity services.
Incorrect Answers
Periodic reporting compares actual progress with approved milestones before final delivery. This evidence would be useful for another condition (The project plan uses milestones without intermediate checkpoints and the sponsor cannot detect drift until the end.) and its different action (Define baselines recurring review cadence and interim milestone measures.). At Evergreen Hospital, it does not demonstrate the required project outcome: An operations representative completes the handoff checklist and accepts ownership.
A budget review includes license support and transition obligations with accountable owners. This evidence would be useful for another condition (A project budget omits third-party subscriptions and support despite planning the first release and operational handoff.) and its different action (Estimate capital operating procurement and transition costs in the baseline budget.). At Evergreen Hospital, it does not demonstrate the required project outcome: An operations representative completes the handoff checklist and accepts ownership.
A training assessment confirms the assigned analysts can perform the planned platform tasks. This evidence would be useful for another condition (A project team expects new analysts to configure an unfamiliar platform without allocating onboarding or learning time.) and its different action (Include necessary staff training and skill development in the resource and schedule plan.). At Evergreen Hospital, it does not demonstrate the required project outcome: An operations representative completes the handoff checklist and accepts ownership.