Question 320
During a project kickoff preparation at Brightstone Legal, the project coordinator identifies an issue: A requirements workshop has no facilitator and one senior participant prevents other departments from describing needs. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The workshop record includes contributions and unresolved requirements from all invited groups. This is the relevant acceptance evidence because it tests whether the corrective action (Assign a neutral facilitator and structured participation rules for the collaborative session.) fixed the original concern (A requirements workshop has no facilitator and one senior participant prevents other departments from describing needs.) at Brightstone Legal, rather than relying only on a task marked complete. The affected work concerns matter files and sensitive case records.
Incorrect Answers
The standup captures blockers promptly while technical decisions receive a dedicated session. This evidence would be useful for another condition (A daily standup repeatedly lasts two hours because the facilitator invites detailed architectural debates.) and its different action (Timebox the standup to coordination and move complex design discussions to a separate workshop.). At Brightstone Legal, it does not demonstrate the required project outcome: The workshop record includes contributions and unresolved requirements from all invited groups.
The next meeting can trace the recorded actions to accountable owners and completion updates. This evidence would be useful for another condition (A weekly steering committee call ends with opinions but no decisions owners or action deadlines recorded.) and its different action (Publish a focused agenda and minutes containing decisions actions owners and due dates.). At Brightstone Legal, it does not demonstrate the required project outcome: The workshop record includes contributions and unresolved requirements from all invited groups.
The published minutes identify the milestone decision authorized attendees and required follow-up. This evidence would be useful for another condition (A meeting contains a decision to alter a contract milestone but the PM relies on memory instead of recording the decision.) and its different action (Assign a scribe and distribute accurate decision minutes for approval and retention.). At Brightstone Legal, it does not demonstrate the required project outcome: The workshop record includes contributions and unresolved requirements from all invited groups.