Question 1180
During an IT infrastructure modernization at Evermere Health, the sponsor representative identifies an issue: Customers first hear about a planned service outage after the team begins database maintenance. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The change ticket records recipients timing and the approved maintenance notice. This is the relevant acceptance evidence because it tests whether the corrective action (Notify affected users through the required change communication process before the window.) fixed the original concern (Customers first hear about a planned service outage after the team begins database maintenance.) at Evermere Health, rather than relying only on a task marked complete. The affected work concerns care team access and regulated data handling.
Incorrect Answers
The approved calendar shows change timing service owner consent and notification lead time. This evidence would be useful for another condition (A production network upgrade is scheduled at noon without checking business downtime commitments or approving a maintenance window.) and its different action (Plan and authorize an operational change window consistent with service impact constraints.). At Evermere Health, it does not demonstrate the required project outcome: The change ticket records recipients timing and the approved maintenance notice.
The deployment log links a passing staging test to an approved production release. This evidence would be useful for another condition (A software team deploys directly into production after coding with no separate staging verification or release approval.) and its different action (Test the change in an appropriate nonproduction environment and obtain documented release authorization.). At Evermere Health, it does not demonstrate the required project outcome: The change ticket records recipients timing and the approved maintenance notice.
A controlled failure rehearsal restores approved connectivity within the recovery objective. This evidence would be useful for another condition (A cloud firewall update is approved but no recovery procedure exists if legitimate traffic is accidentally blocked.) and its different action (Document and test a rollback plan and validation checks before the production change.). At Evermere Health, it does not demonstrate the required project outcome: The change ticket records recipients timing and the approved maintenance notice.