Question 540
A hotel security upgrade schedule ignores lead times for specialized locks, leaving guest entrances temporarily unprotected during renovation. The manager proposes this correction: Build a staged implementation plan with procurement milestones, risk controls and temporary security coverage. Which ongoing control would BEST reduce recurrence of this specific failure?
Explanation
Correct Answer
Maintain change-control and contingency reserves for long-lead critical security components. This sustains the corrective step — build a staged implementation plan with procurement milestones, risk controls and temporary security coverage. — and targets the weakness: Project sequencing overlooked procurement risks and interim protective measures.
Incorrect Answers
Retest after system upgrades and periodically sample terminated credentials. The control concerns: Commissioning does not test authorization lifecycle and critical failure conditions. It does not specifically prevent recurrence of: Project sequencing overlooked procurement risks and interim protective measures. The direct preventive step is: Maintain change-control and contingency reserves for long-lead critical security components.
This routine protects against: Predictive and preventive checks do not cover a critical mechanical failure mode. For the described failure, the relevant recurring check is: Maintain change-control and contingency reserves for long-lead critical security components.
The proposed safeguard is intended for: The survey does not account for real movement paths and response coverage around exits. The reported issue originates from: Project sequencing overlooked procurement risks and interim protective measures. The targeted prevention is: Maintain change-control and contingency reserves for long-lead critical security components.